By Jennifer Freer, Staff Writer
The General Services Administration is scrambling to get back on track its massive $5 billion long-distance service program that is as much as three months behind schedule.
While 27 percent of federal agencies already have transitioned to the new contract, called FTS2001, that percentage is nearly 15 percent less than planned at this time, said officials with the GSA Federal Technology Service branch, which is administering the telecommunications contract.
The delays could be costly for FTS2001 vendors MCI WorldCom Inc. of Clinton, Miss., and Sprint Corp. of Westwood, Kan., if government agencies are not ready by the Dec. 6 deadline, according to government and industry officials.
And the delays also hurt the federal agencies, which are losing potential savings from the new long-distance contracts.
GSA officials, however, are confident the transition to the FTS2001 contract from FTS2000 can be completed by the planned deadline.
The GSA doesnt consider the transition way behind, said Frank Lalley, GSAs FTS assistant commissioner for service delivery. Some agencies didnt want to move earlier because of Y2K problems. Every agency has plans to move by December 2000, and hopefully most agencies will be finished by September.
However, some in government and industry are doubtful and, speaking on background, said that the GSA likely will have to extend the existing FTS2000 contract with AT&T Corp. after the December deadline.
The FTS2001 is GSAs long-distance telecommunications contract to provide government agencies with long-distance, data and video services.
Awarded to MCI and Sprint in early 1999, the contract has an expected value of $5 billion over eight years.
Each company is guaranteed at least $750 million in long-distance contracts from federal agencies, and then must compete head to head for the rest of the potential business.
The GSA set up the Technical and Management Support Services contracts to help government agencies get support service to speed the transition to FTS2001, but the contract are not being used widely, according to government and industry officials. The TMS contracts were awarded to six system integrators in September 1997 and is valued at $3 billion (See related story).
The FTS2001 problems and delays were discussed at a March 22 meeting of the Telecom Shared Interest Group.
The organization consists of telecommunications heavyweights such as AT&T, Bell Atlantic Corp., GTE Corp., MCI, Sprint and US West, as well as Competitive Local Exchange Carriers, GSA officials and industry consultants.
The transition from FTS2000 to FTS2001 is the largest in the history of telecommunications, said John Johnson, who chairs an interagency task force established in October 1999 to provide a forum for customer agencies, the GSA and contractors to address common problems.
There are, for example, 272,000 circuits that have to be switched over, involving 200 government agencies and 23,100 locations in 7,000 cities.
Federal agencies were supposed to begin transitioning to the new FTS2001 contracts in July 1999, but did not begin until October. As of March, just 27 percent of the agencies had made the transition, short of the goal of 40 percent.
The delays are hitting government agencies in the wallet because they must wait to obtain the lower prices in the FTS2001 contracts for long-distance, data, video and other services, Johnson said.
The delays also prevent government agencies from building for the future, Lalley said. The agencies must rely on the old way of doing business, with older technology and fewer service options, he added.
Meanwhile, the longer it takes government agencies to transition to the new contract, the longer MCI and Sprint must wait to reap the financial benefits, said Johnson and Lalley.
Government and industry officials could not put a precise figure on the potential losses to vendors and agencies caused by the delays.
Officials agreed that government and industry shared blame for problems and delays in transitioning to FTS2001.
Most of the FTS2001 problems identified by the Telecom SIG fell into three categories: constructing facilities and networks; gaining access to location sites in remote rural areas where service is needed; and ordering services. The ordering process accounted for about 70 percent of problems and delays.
The main problem with the ordering process is that, because ordering is done electronically, the system is very rigid, according to officials.
An order will be rejected, for example, if an address on an order is written as Street instead of St. With up to a 50 percent rejection rate on orders, such problems can take days and even to weeks to resolve, Johnson said.
AT&T had the same kind of difficulties 10 years ago when it was awarded the original FTS contract, said an AT&T executive at the meeting. When the ordering system was not automated, it was handled by people who knew that Street and St. are synonymous. But computers must be pro-grammed to make such judgments.
Theres not one quick fix to this issue, Johnson said.




